What is evaluated during the Foundations stage of DSDM?

  1. Requirements Gathering

  2. Risk Assessment

  3. User Feedback

  4. Deployment Strategies

The correct answer is: Risk Assessment

During the Foundations stage of DSDM (Dynamic Systems Development Method), the primary focus is on establishing a clear understanding of the project's scope and objectives. This stage is crucial for setting the groundwork for the entire project to ensure a solid foundation for successful development. Risk Assessment is a key activity during this stage as it involves identifying any potential risks that could impact the project's success. Evaluating risks allows the team to proactively address uncertainties and challenges, ensuring that there are strategies in place to mitigate these risks as the project progresses. This careful consideration of risks helps in managing expectations and aligning the project with the stakeholders' needs and goals. In contrast, activities such as Requirements Gathering are typically more prominent in later stages where detailed requirements are established based on the foundational understanding. User Feedback and Deployment Strategies are also more relevant during later phases, emphasizing the iterative nature of DSDM where feedback loops and deployment considerations come into play after the foundational elements have been solidified.